FIRST REPORT ON THE RESCUE OF HUMAN REMAINS FROM BURIALS DISTURBED BY DEVELOPMENT WORK AT THE OLD BURIAL GROUND, GREENPOINT, KIMBERLEY
8 December 2004
David Morris and Elizabeth A Voigt
McGregor Museum, Kimberley
Introduction
During the excavation of trenches for services in Greenpoint in January 1995 a number of burials were revealed and some of the remains retrieved (see report by Voigt, Jonk and Barbour 1995). The remains were extensively damaged. They were re-interred at a ceremony at Greenpoint on 24 September 2004. Archival research showed that the soccer field along Dutch Reformed Road where the trench was dug covered a cemetery dating from 1880 until 1913. Alignment of the old maps and the new plans was not easy. When work on the new phase of housing proceeded earlier in 2004, no impact assessment at this highly sensitive area was carried out, and a similar situation arose with a major trench cutting through a line of perhaps fifty or more graves. Half the trench was filled in again before it came to the attention of the Provincial Heritage Unit and the South African Heritage Resources Agency (SAHRA), who halted development at the trench site at the end of July 2004.
In terms of the South African Heritage Resources Act (25 of 1999) the disturbance of burials that are older than 60 years and are outside a demarcated cemetery must be subject to investigation by an archaeologist and in terms of a permit issued by SAHRA. Upon advice of SAHRA, the McGregor Museum met with the legal representative of the Sol Plaatje Municipality on the procedure to be followed, and signed a permit application in the first week of August. After long delays at Sol Plaatje the permit application and contract agreement were signed by the Acting City Manager, and a permit was issued by SAHRA on 15 November. The Museum was given responsibility and authorisation for the investigation and rescue of the remains, and the second author, who is a qualified archaeologist, was contracted to supervise the undertaking.
A team of persons, mainly Kimberley community members, several of whom have previous experience in disinterments, began work on site in November. Prior to this, Mr Morris had walked over the disturbed area and plotted and retrieved human bones from the surface of the dumps on the north eastern side of the trench. It was therefore decided that the dumps would have to be sieved for remains at the same time that the graves were investigated and rescued, as necessary.
Procedure
The field team was put to work immediately sieving the dumps. This is an enormous and not very exciting task which requires trained eyes and a great deal of patience. The dumps consist of large quantities of broken shale (the country rock) mixed with grave contents and the overlying soils. A lot of animal bone has been retrieved from the transverse trench described below, and a small amount of human remains have been found in the dumps which have so far been processed.
In the week of 15th November the field supervisor (EAV) plotted the position of 25 graves visible in the section of the trench which had not been backfilled. A long section of the trench had already been back-filled; graves there would have been disturbed and severely damaged, and some bones had been retrieved from the surface in that section. Work was then begun at the north western end of the trench, where the dumps were being sieved, systematically investigating and rescuing what remained of the damaged graves.
The grave fill was removed until bone was found, then trained excavators took over and uncovered the skeletons. Once fully exposed, each skeleton or part thereof is measured three dimensionally and photographed before it is lifted and packed into a box for transportation to the Museum for further assessment and temporary storage prior to re-interment as per discussions with the community (community consultation on this cemetery has been under way since November 2003, mainly in relation to the reburial of the remains rescued in 1995). The excavation of the skeletons is extremely difficult as the bone is in a very fragile condition and breaks up into splinters as the skeleton is uncovered. In addition, all the skulls found so far have been totally crushed. This is not easy to explain, with one possibility being that a roadway ran above the graves at some stage. It could also be that the grave fill, being mainly broken shale with little in the way of clay or sand matrix was less inclined either trickle into bone cavities and/or to consolidate around the outside.
Preliminary findings.
The cemetery is not aligned as others have tended to be on an east-west axis, so that in this case the majority of graves lie south-east to north-west, with two crossing north-east to south-west. In the trench dug in 1995 all the graves lay north-east to south-west.
It was initially assumed that the majority of the skeletons had been extensively damaged and that complete skeletons would be the exception. However, at the time of writing this report, only two of the graves were found to have been truncated to such an extent that the skeletons had themselves been impacted. In the rest, while the grave had been cut open down one side, the skeletons survived almost intact. The depths of the graves differs; so far most are less than a metre below the original ground surface. This corroborates contemporary reports on the cemetery, in which comments were made concerning the shallowness of the graves. It also correlates with what was found in 1995.
Nine graves have so far been examined and work on seven of them has been completed. Two of the graves on the south-western side of the trench each contained three skeletons. One grave on the north-eastern side originally contained two skeletons, one of which was mostly destroyed by the trench digging operation. One other skeleton on the north-eastern side has been mostly disturbed by the trench - only the left arm and leg remained in the grave. Thus the nine graves have yielded the partial or complete remains of 14 individuals.
Several of the skeletons have associated grave goods in the form of iron and copper bangles. This is consistent with what was found at the excavations outside Gladstone Cemetery (2003) and is a strong indication that the burials are of Black persons, probably migrant mine workers. Old plans and maps (1886 and 1899-1900) show that the cemetery was divided into two, referred to as “Malay” and “Native” (terminology from 1899-1900 map).
A major concern is the need to define the northern edge of the cemetery. To this end, a transverse trench three metres wide has been dug northwards from the trench in the vicinity of Grave N7. The trench has been cleared to bedrock. A lot of bone and glass was found in an ash deposit lying across one section, but no signs of any graves were found. In addition, the remains of an iron fence post, set in concrete but corroded off at ground level, was found in the north-eatern wall of Grave N9. We believe that this was probably one of the fence posts of a boundary fence of the cemetery (the fact that it intersects the edge of the grave is an indication that it was erected after the grave was dug and possibly when the cemetery edge was no longer clearly known). It is singularly unfortunate that the trench has gone through the last two lines of graves in the cemetery. At the south eastern end of the trench, at Dutch Reform Road, another two lines of graves were observed to run north-east of the trench. It is possible that the trench runs at a slight angle from the alignment of the rows of graves; or that additional rows of graves exist at that lower corner of the cemetery.
The higher than expected number of skeletons needing to be rescued, coupled with the very poor state of preservation of the bone (which necessitates extreme caution), is slowing down the excavation procedure. We have four excavators working on the skeletons with one field assistant opening up the grave to “bone level”. The rest of the team of twelve is occupied in sieving the dumps.
Continuation of work
The investigation and rescue of the graves as required by the National Heritage Resources Act is going to take considerable time. The operation will close down temporarily on 22 December until the beginning of the new year. In January, work will recommence and will concentrate on the dumps.
The material at the Museum will be examined by a specialist in order to define age, sex, population affinities, health status and any other information that would help restore dignity to the individuals whose remains and graves were disturbed by the trench. This work will begin in the new year and run concurrently with the excavations. All fieldwork is subject to the weather; if we experience heavy rains in January and February this will affect the work programme.
McGregor Museum
8 December 2004